Jira burndown chart: how to read it and why it sometimes looks wrong

The burndown chart shows how much work is left in a sprint. Most questions about it come from three settings: the board filter, the column mapping and subtasks. Here is how it works in company-managed Jira spaces.

Updated

What it shows

Atlassian describes the burndown chart as showing the actual and estimated amount of work to be done in a sprint: time runs along the horizontal axis, remaining work along the vertical one. Its purpose is to track the total work remaining and to project whether the team will reach the sprint goal, so the team can react while the sprint is still running. It applies only to scrum boards.

Open it

Select the space, open the Reports tab and choose Burndown Chart. Use the sprint drop-down to switch sprints and the estimation statistic drop-down to change what is counted; that choice is saved for your next visit. How to read this chart at the top gives a short description.

Three settings behind every burndown

The board filter. The chart only includes work items that match your board's saved filter. Work outside the filter does not burn down, even if it is in the sprint by name.

The column mapping. A work item counts as To Do when its status maps to the left-most column, and as Done when it maps to the right-most column. A status left in a middle column never burns down.

The estimation statistic. The vertical axis uses the statistic configured for the board, such as story points.

Subtasks and missing guidelines

Story points on subtasks are not included; only points on parent work items count. Adding a subtask to a work item already in an active sprint is treated as a scope change. Whether that shows on the chart, and whether subtask time estimates roll up to the parent, depends on whether remaining estimate and time spent is enabled for the board.

If the grey guideline is missing, Atlassian notes that the sprint may have been started before any work items were assigned to it.

Reading it honestly

A flat line for the first days, then a cliff on the last, usually means work is only being moved to Done at the end, not that nothing happened. A line that rises means scope was added. Both are worth discussing in the retrospective; neither is fixed by changing the chart.

Sources

  1. Atlassian Support: View and understand the burndown chart

Questions and answers

Where is the burndown chart in Jira?

In the space, open Reports and choose Burndown Chart. It is available on scrum boards.

Why does my Jira burndown chart not go down?

Work items count as done only when their status maps to the right-most board column, and only items in the board's filter are counted.

Are subtasks included in the Jira burndown chart?

Story points on subtasks are not included; only story points on parent work items count.

How to cite this

Going Stellar (2026). Jira burndown chart: how to read it and why it sometimes looks wrong. GOING STELLAR S.R.L..
https://goingstellar.ro/methods/jira-burndown-chart/

Read as Markdown

All methods

Contact

Tell us what is not working

Write in English or Romanian. A person reads it — usually the same person who would do the work — and answers within one business day.