# Jira burndown chart: how to read it and why it sometimes looks wrong

*The burndown chart shows how much work is left in a sprint. Most questions about it come from three settings: the board filter, the column mapping and subtasks. Here is how it works in company-managed Jira spaces.*

> Jira · Scrum · Reports · 2026-11-29 · https://goingstellar.ro/methods/jira-burndown-chart/

## Key points

- The burndown chart shows remaining work in a sprint and applies only to scrum boards.
- It includes only work items that match the board's saved filter.
- Done means the status is mapped to the board's right-most column.
- Story points on subtasks are not counted; only parent work items are.
- A missing guideline can mean the sprint started before items were added.

## What it shows

Atlassian describes the burndown chart as showing the actual and estimated amount of work to be done in a sprint: time runs along the horizontal axis, remaining work along the vertical one. Its purpose is to track the total work remaining and to project whether the team will reach the sprint goal, so the team can react while the sprint is still running. It applies only to scrum boards.

## Open it

Select the space, open the **Reports** tab and choose **Burndown Chart**. Use the sprint drop-down to switch sprints and the estimation statistic drop-down to change what is counted; that choice is saved for your next visit. **How to read this chart** at the top gives a short description.

## Three settings behind every burndown

**The board filter.** The chart only includes work items that match your board's saved filter. Work outside the filter does not burn down, even if it is in the sprint by name.

**The column mapping.** A work item counts as To Do when its status maps to the left-most column, and as Done when it maps to the right-most column. A status left in a middle column never burns down.

**The estimation statistic.** The vertical axis uses the statistic configured for the board, such as story points.

## Subtasks and missing guidelines

Story points on subtasks are not included; only points on parent work items count. Adding a subtask to a work item already in an active sprint is treated as a scope change. Whether that shows on the chart, and whether subtask time estimates roll up to the parent, depends on whether remaining estimate and time spent is enabled for the board.

If the grey guideline is missing, Atlassian notes that the sprint may have been started before any work items were assigned to it.

## Reading it honestly

A flat line for the first days, then a cliff on the last, usually means work is only being moved to Done at the end, not that nothing happened. A line that rises means scope was added. Both are worth discussing in the retrospective; neither is fixed by changing the chart.

## Sources

1. [Atlassian Support: View and understand the burndown chart](https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-burndown-chart/)

## Questions and answers

### Where is the burndown chart in Jira?

In the space, open Reports and choose Burndown Chart. It is available on scrum boards.

### Why does my Jira burndown chart not go down?

Work items count as done only when their status maps to the right-most board column, and only items in the board's filter are counted.

### Are subtasks included in the Jira burndown chart?

Story points on subtasks are not included; only story points on parent work items count.

## How to cite

**Cite this as:** Going Stellar (2026). *Jira burndown chart: how to read it and why it sometimes looks wrong*. GOING STELLAR S.R.L.. https://goingstellar.ro/methods/jira-burndown-chart/

```bibtex
@misc{goingstellar2026jira,
  title  = {Jira burndown chart: how to read it and why it sometimes looks wrong},
  author = {{Going Stellar}},
  year   = {2026},
  url    = {https://goingstellar.ro/methods/jira-burndown-chart/},
  note   = {2026-11-29}
}
```

Licence. Free to quote with attribution.

## Also available

- This page as HTML: https://goingstellar.ro/methods/jira-burndown-chart/
- Same article in Romanian: https://goingstellar.ro/ro/metode/graficul-burndown-in-jira/