Jira reminders before a release date or sprint end
A release has a date and a sprint has an end, but the issues inside them do not inherit either. Reminders in Jira, native or not, mostly work from an issue's due date. Here is how to find the work at risk, how to give it a due date that follows the release, and what an app can do from there.
Updated
Why the release date does not remind anyone
In Jira, a release is a version with its own dates, and an issue belongs to it through the Fix versions field. A sprint has a start and an end on the board. Neither date is copied to the issues: an issue in next Friday's release has no due date unless someone sets one.
That matters because the tools that send reminders look at issues. A filter subscription emails the issues a search returns. An Automation rule acts on issues. Reminder apps, ours included, read the due date field. So there are two steps: find the work that belongs to the release or sprint, then decide whether to give it a due date.
Step 1: find the open work in a release or sprint
JQL has functions for both. For releases:
fixVersion = earliestUnreleasedVersion(ABC) AND statusCategory != Done returns what is still open in the next release of project ABC. Atlassian's reference notes that the order comes from the Releases page: the version at the bottom of the list counts as the earliest, and you can reorder them by dragging. fixVersion in unreleasedVersions() covers every release that has not shipped yet.
For sprints, sprint in openSprints() AND statusCategory != Done returns the open work in sprints that have started but not been completed, and futureSprints() the ones not started yet.
Note what these do not do: they search by version or sprint, not by its date. The JQL reference describes searching fix versions by name or ID. To get “due within a week” you need a date on the issue.
Step 2: a list on a schedule
The lightest native reminder is a filter subscription. Save the release search as a filter and subscribe the team to it, weekly or on the mornings before a release; with the Advanced schedule you enter a cron expression. Everyone gets the same list, up to the first 200 results. It names the open work, but it does not tell any one person that their issue is late.
Step 3: give issues a due date that follows the release
If you want reminders per issue, the issues need due dates. Two native ways:
Bulk edit. Run the release search, select the issues in the list and edit them together; Atlassian's documentation says you can edit fields on up to 1,000 work items at a time. Set the due date to the release date, or a few days before it if testing needs time. It is quick, but you repeat it whenever the release moves or new issues join.
An Automation rule. Automation has a trigger for versions being created, updated or released, and a branch, Work item fixed in version, that loops over the issues in that version. In an Edit work item action, the smart value {{issue.fixVersions.releaseDate}} returns the fix version's release date. Test it on a copy first: it is cleanest when each issue has one fix version, because with several the smart value refers to all of them.
Sprints are less tidy. Automation can react when a sprint is created, started or completed, but none of those fire a few days before the sprint ends, so for “the sprint ends Thursday” most teams bulk-edit the due dates when the sprint starts, or rely on the board itself.
Where Deadliner helps
Deadliner is our app for the last step. It does not read release or sprint dates; it reads the due date. Once the issues in a release have due dates, it takes the reminders off your hands. You turn it on per project; once a day it posts a comment that mentions the assignee before an issue is due, and one when it becomes overdue, with the date it was due.
Reminders are kept per issue and due date. When a release slips and you move the due dates, the new date gets its own reminder, without duplicates for the old one. Without a paid licence the warning comes two days before the due date; with one you choose between one and thirty days, which is useful when “due” means “ready for the release”.
The project page lists what is overdue and what is due soon, and an optional daily digest emails the project lead one list of both. It does not use your Automation rule runs.
What Deadliner does not do
It does not know about sprints or versions. Issues without a due date are ignored, so if your release work has none, Deadliner has nothing to remind about until Step 3 is done. It does not move due dates when a release moves; that is the bulk edit or the Automation rule.
Assignees are mentioned; unassigned issues get no comment, though they appear on the project page and in the digest. Each daily pass looks at the first hundred matching issues per project, ordered by due date, and dates are compared in UTC. The digest goes only to the project lead.
Sources
- Atlassian Support: JQL functions (earliestUnreleasedVersion, openSprints)
- Atlassian Support: JQL fields (Fix version, Sprint)
- Atlassian Support: Manage filters (subscriptions)
- Atlassian Support: Edit multiple work items
- Atlassian Support: Jira automation triggers
- Atlassian Support: Jira smart values for issues
- Atlassian Marketplace: Deadliner
Questions and answers
Does Jira remind people before a release date?
Not by default. The release date sits on the version, not on the issues. Use a filter subscription for a list, or give the issues due dates and remind from those.
How do I find unfinished issues in the next release?
Use fixVersion = earliestUnreleasedVersion(ABC) AND statusCategory != Done. The earliest version is the one at the bottom of the project's Releases page.
Can Automation copy the release date to the due date?
Atlassian documents a smart value, {{issue.fixVersions.releaseDate}}, that returns the fix version's release date, and a Work item fixed in version branch. Test the rule first, especially on issues with more than one fix version.
Does Deadliner read sprint or release dates?
No. It works from the due date field. Once issues have due dates, it reminds the assignee before the date and once when the issue is overdue.