Jira automation for due dates: rules, schedule, limits

A scheduled automation rule can remind people before a Jira due date and once when it is missed. Here are two rules you can copy, the JQL that stops daily repeats, and what they cost in automation steps, which Atlassian starts billing on 3 December 2026.

Updated

Rules are now called flows

Atlassian's documentation now calls automation rules "flows", and issues "work items". The ideas are the same. A flow has a trigger, optional conditions and branches, and actions. For due dates, the trigger has to be Scheduled: no event fires when a date gets closer, so nothing else would start the flow.

How the Scheduled trigger works

The Scheduled trigger runs at a fixed rate, for example every 7 days, or on a cron expression for more complex schedules. You can add a JQL query; the actions then run on the work items it returns.

Four limits from Atlassian's service limits page (checked on 29 November 2026) matter here. A scheduled JQL search uses at most 999 work items. Only one run of the same scheduled flow can happen at a time. A scheduled flow that fails 10 times in a row disables itself. And the trigger has an option to only include work items that changed since the last run. Atlassian suggests it to keep flows small, but leave it off here: a work item whose due date is getting closer usually has not changed at all.

Flow 1: a reminder two days before the due date

Trigger: Scheduled, once a day, with this JQL:

dueDate >= startOfDay("+2d") AND dueDate < startOfDay("+3d") AND statusCategory != Done

The window is one day wide on purpose. startOfDay("+2d") is the start of the day after tomorrow, and the query stops before the day after that, so each work item matches on exactly one run. A wider query such as dueDate <= 2d matches again every day until the work is done, and the assignee gets the same email every day, overdue days included.

Action: Send customized email to the assignee. The older Send email action is deprecated, and Atlassian migrates existing flows to the new one. A body with date smart values:

{{issue.key}} is due on {{issue.duedate.format("dd/MM/yyyy")}}, in {{now.diff(issue.duedate).businessDays}} business days.

diff returns the time between two dates in the unit you ask for, including businessDays; it is negative when the second date is earlier than the first. If you want to check the count by hand, our business days calculator does the same arithmetic.

Flow 2: one message the day after it is missed

Same trigger, same once-a-day schedule, with the window moved to yesterday:

dueDate >= startOfDay("-1d") AND dueDate < startOfDay() AND statusCategory != Done

This matches a work item once, on the first day it is overdue. For a comment on the work item instead of an email, use the Add comment action; the reminder then stays in the history where the whole team sees it. If you want a weekly nudge for everything still late, run a separate weekly flow on dueDate < startOfDay() AND statusCategory != Done and send one summary rather than one message per work item.

What these flows cost in steps

Atlassian measures automation usage in steps. Each trigger, condition, action, branch and loop that runs counts as one step; a loop or branch counts once, plus the steps that run inside it. Some steps never count, such as Log action and Lookup work items, and from 5 November 2026 runs that perform no actions are not charged. Usage-based billing starts on 3 December 2026.

The figures in this section were checked on 29 November 2026 against Atlassian's pages How is your automation usage calculated and Automation service limits. They change, so check both before you plan around them.

Atlassian's own example is close to ours: a flow scheduled every day at 9:00 with a loop that runs three times and creates a work item each time uses five steps, one for the trigger, one for the loop and three for the actions.

Monthly allowances for Jira, pooled across the organization: Free 150 steps per subscription, Standard 400 per user, Premium 750 per user, Enterprise 1,000 per user. On Free, 150 steps a month is about five a day, so two daily reminder flows can use it up. With pay as you go turned on, extra steps cost $0.50 per 1,000. With it off, flows stop at 100% until the allowance resets.

Two more limits catch small teams. On the Free plan, the email actions send at most 100 emails in 24 hours. And the number of flows running at the same time is 5 on Free, 10 on Standard, 20 on Premium and 30 on Enterprise. Admins can see which flows use the most steps under Settings → System → Global automation → Usage.

When a flow is the wrong tool

A flow per space works well when one admin owns it and the windows above are right. It gets harder when every team wants its own lead time, when you need the reminder on many spaces at once, or when the step allowance is tight.

That is the gap Deadliner fills. It reminds the assignee before the due date and once when it is overdue, without duplicates. Deadliner runs on a Forge scheduled trigger, not as a Jira Automation rule, so it does not count toward automation steps. Our other guides compare it with the native options: due date reminders in Jira and finding overdue Jira issues.

Sources

  1. Atlassian Support: How is your automation usage calculated
  2. Atlassian Support: Automation service limits
  3. Atlassian Support: Jira automation triggers (Scheduled)
  4. Atlassian Support: Jira smart values, date and time
  5. Atlassian Support: Jira automation actions (Send customized email)
  6. Atlassian Support: JQL functions (startOfDay)
  7. Atlassian Marketplace: Deadliner

Questions and answers

How do I create a Jira automation rule for due dates?

Use the Scheduled trigger once a day with a JQL query for work items due in a set window, for example dueDate >= startOfDay("+2d") AND dueDate < startOfDay("+3d") AND statusCategory != Done, then add a Send customized email or Add comment action.

Why does my Jira automation send the same reminder every day?

The JQL window is open-ended, such as dueDate <= 2d, so the work item matches on every run until it is done. Narrow it to a single day.

What are the Jira automation limits on the Free plan?

150 automation steps a month per subscription, 100 automation emails in 24 hours, 5 flows running at the same time, and 999 work items per scheduled JQL search.

How are Jira automation steps counted?

Each trigger, condition, action, branch and loop that runs is one step. A loop or branch counts once, plus the steps inside it. Log action, Lookup work items and runs with no actions performed are not counted.

How to cite this

Going Stellar (2026). Jira automation for due dates: rules, schedule, limits. GOING STELLAR S.R.L..
https://goingstellar.ro/methods/jira-automation-due-date-overdue-rules/

Read as Markdown

All methods

Contact

Tell us what is not working

Write in English or Romanian. A person reads it — usually the same person who would do the work — and answers within one business day.