How do you follow Jira dependency chains across projects?

Jira can link one issue to another, search those links and draw some of them on a timeline. What it does not do on its own is follow the chain: what blocks the thing that blocks you. Here is how to get as far as possible natively, and where an app saves the clicking.

Updated

Start with one link type

A dependency in Jira is an issue link. The default link types include blocks / is blocked by, relates to, duplicates, clones and causes, and Jira admins can add their own. Each link type has a name, an outward description (how this issue affects the other) and an inward description (how it is affected).

The first decision is the one that makes everything else work: use one link type for “this cannot finish until that is done”, and use it everywhere. Most teams use Blocks, and Jira's own views assume it. The space timeline can only show the Blocks link type. Plans (Premium and Enterprise) treat every link type they show as if it were Blocks.

That is also the honest answer to “blocked by or depends on?”. There is no built-in depends-on type. An admin can create one, but then you have two words for the same thing, and the views that read Blocks will not see half of your dependencies. If people prefer to say “depends on”, say it in the summary or the description and still link with Blocks. Keep relates to for “worth reading together”, not for order of work.

Find direct dependencies with JQL

JQL can search links in both directions. Atlassian's reference gives these forms, where ABC-123 is the issue you care about:

workItemLink["blocks"] = ABC-123 finds the issues that block ABC-123, the ones it is waiting on.

workItemLink["is blocked by"] = ABC-123 finds the issues that ABC-123 blocks, the ones waiting on it.

The function linkedWorkItems(ABC-123) finds every issue linked to ABC-123, and you can pass one or more link types to narrow it, and workItemLinkType = "is blocked by" finds every issue that has at least one blocker. Older guides use the names issueLinkType and linkedIssues(); the current reference uses the work-item names.

Add AND statusCategory != Done to see only what is still open. Links can point to any project on the same Jira site, so these searches already work across projects; the reference notes that links to issues on another Jira site are not included.

Where the native options stop

JQL returns one step. Each search above gives you the issues directly linked to ABC-123. To see what blocks those, you run the search again for each result, and again for the next level. On a real programme that is where the time goes, and where people give up and draw the chain in a slide.

The space timeline is limited to one space. It draws Blocks dependencies between issues, but Atlassian's documentation says it can only link issues from a single space, so a dependency on another team's project does not appear there.

Plans can show more, on Premium and Enterprise. A plan can bring together work from several spaces, and its Dependencies view shows issues as tiles with arrows between them. If you already pay for Premium, build a plan around the projects involved and start there. Your admin can configure which link types the plan shows.

Whatever you use, a dependency is only as good as its link. A once-a-week search for open issues with workItemLinkType = "is blocked by" is a cheap way to review what your projects say is blocked, and to remove links that are no longer true.

Where Dep Chains helps

Dep Chains is our app for this. It adds a panel to every issue with two lists: Waiting on, what must finish before this issue, and Blocking others, what waits on it. Each list is grouped by distance, starting with the directly linked issues, then those two steps away, and so on, with the status and assignee of each one. A line at the top says how many unfinished issues stand between this one and being unblocked.

It follows Blocks links into any project the person looking can see, because it reads Jira as that person. Loops in the links do not break it. It only reads: the app has no permission to change issues or links. Relates to links are not followed, so the lists stay about order of work.

Without a paid licence the panel follows two steps in each direction; with one it follows three. A project page, What's blocked, lists the unfinished issues in a project that wait on other unfinished issues, the most blocked first, with up to five of their open blockers. Without a licence it shows the top five; with one it shows up to fifty and can show the full list as CSV text to copy.

What Dep Chains does not do

It only follows link types whose name contains “block”, which is the standard Blocks type. A custom “depends on” type is not followed, which is one more reason to use Blocks.

It does not draw a graph or a timeline, and it does not plan dates or a critical path; it lists the chain in steps. In very large chains it stops after four hundred linked issues in a direction and says so. The project page looks at the hundred most recently created unfinished issues in the project, and at their direct blockers only, not the whole chain behind them.

It sends no notifications and changes nothing, so keeping the links true is still the team's job.

Sources

  1. Atlassian Support: Link work items (link types)
  2. Atlassian Support: Configure work item linking
  3. Atlassian Support: JQL fields (Work item link)
  4. Atlassian Support: JQL functions (linkedWorkItems)
  5. Atlassian Support: Dependencies on the timeline
  6. Atlassian Support: What are dependencies in your plan?
  7. Atlassian Support: The dependencies view in your plan
  8. Atlassian Support: Plan and view work across multiple spaces
  9. Atlassian Marketplace: Dep Chains

Questions and answers

What is the difference between "blocks" and "is blocked by" in Jira?

They are the two descriptions of the same Blocks link, one for each issue. If A blocks B, then B is blocked by A; you create the link once.

Does Jira have a "depends on" link type?

Not by default. An admin can create one, but the space timeline only shows Blocks, so most teams link dependencies with Blocks and keep a single type.

Can JQL find dependencies in another project?

Yes. Links can point to any project on the same Jira site, and JQL searches them all. Links to issues on another Jira site are not included.

Can Jira show a whole dependency chain?

JQL returns direct links only, and the space timeline shows links within one space. Plans on Premium and Enterprise has a Dependencies view; otherwise you follow the chain one search at a time or use an app.

How to cite this

Going Stellar (2026). How do you follow Jira dependency chains across projects?. GOING STELLAR S.R.L..
https://goingstellar.ro/methods/jira-dependency-chains-across-projects/

Read as Markdown

All methods

Contact

Tell us what is not working

Write in English or Romanian. A person reads it — usually the same person who would do the work — and answers within one business day.