Jira · Calendar · Due dates
Jira calendar view: due dates, start dates, overdue
Every Jira space has a calendar that places work by its start and due dates. Here is what appears on it, how to schedule and move work from the calendar, how it marks overdue work, and what it does not do.
Updated
Where the calendar is and what it shows
Open the space and select Calendar in the space navigation. In software spaces the calendar can also show sprints and releases; business spaces can be set to show software release dates.
It only shows work items that have a Start date or a Due date. Work without dates does not appear. Unlike the calendar in Plans, this one does not place work by the dates of its sprint or release.
Put work on the calendar
Select an empty space on a day, type a summary, pick the work type and select Create: the day you picked becomes the due date. Drag across several days instead, and the first and last day become the start and due date. If the calendar shows more than one space, you choose which space the work belongs to. Creating work this way needs the Create work items permission.
Work that already exists but has no due date waits in Unscheduled work, at the top right. Drag an item from that drawer onto a day to give it that due date. The drawer can be filtered by assignee, priority and status.
Move and stretch work
Drag a work item to another day to change its due date. Drag one of its edges to change only the start date or only the due date. Select it to open the full work item and change anything else.
Read the colours
A work item's colour comes from its status category: grey for To Do, blue for In Progress, green for Done. A red item was not done by its due date and is now overdue.
The filters at the top default to Type, Status and Assignee, with More + for other fields, and the search finds words in the summary or description, or a work item key. View settings → Week starts on sets the first day of the week.
What the calendar does not do
The calendar shows that something is late; it does not tell anyone. Jira's notification schemes react to changes, such as an update or a new assignee, and no event fires when a due date passes, as we explained in our guide to Jira email notifications. Someone still has to open the calendar to see the red items.
Getting a reminder to the assignee takes a filter subscription, a scheduled automation rule or an app. We compared them in due date reminders in Jira.
Where Deadliner fits
Deadliner is our app for that reminder. Turned on for a project, it comments on open issues with a due date and an assignee, @mentioning the assignee before the due date and once when the issue becomes overdue, at most once each per due date. It can also send the project lead one daily e-mail listing what is overdue and due soon. Issues without a due date or without an assignee are skipped, so a due date that puts work on the calendar is also the date Deadliner reminds about.
Sources
Questions and answers
Why is a work item not on the Jira calendar?
It has no start date and no due date. Give it a due date, or drag it from Unscheduled work onto a day.
What does red mean on the Jira calendar?
The work item was not completed before its due date and is now overdue.
Can the Jira calendar send reminders?
No. It shows dates and overdue work. Reminders come from filter subscriptions, scheduled automation rules or a Marketplace app.