NETWORKDAYS in Google Sheets: syntax and examples
NETWORKDAYS counts the days from Monday to Friday between two dates, both ends included. A list of holidays removes more days, so it fits delivery times and invoice terms.
Syntax
NETWORKDAYS(start_date, end_date, [holidays])
Arguments
| Argument | Type | Required | What it does |
|---|---|---|---|
start_date | date | yes | First day of the period, counted if it is a working day. |
end_date | date | yes | Last day of the period, also counted. |
holidays | range | no | Dates to skip, in addition to Saturdays and Sundays. |
Examples
The examples use this table, starting in A1:
| Holidays |
| 46356 |
| 46386 |
=NETWORKDAYS(DATE(2026,11,2), DATE(2026,11,30))Result: 21
Working days in November 2026 from the 2nd to the 30th, weekends excluded.
Run in a Google Sheet (English US locale) on .
=NETWORKDAYS(DATE(2026,11,2), DATE(2026,11,30), A2)Result: 20
The same period minus one holiday (30 November, in A2).
Run in a Google Sheet (English US locale) on .
=NETWORKDAYS(DATE(2026,12,1), DATE(2026,12,31), A2:A3)Result: 22
December with two holidays in the list (30 Nov is outside, 30 Dec is inside).
Run in a Google Sheet (English US locale) on .
=NETWORKDAYS(DATE(2026,11,9), DATE(2026,11,9))Result: 1
Start and end on the same working day count as 1.
Run in a Google Sheet (English US locale) on .
=NETWORKDAYS(DATE(2026,11,30), DATE(2026,11,2))Result: -21
Start after end: the result is negative.
Run in a Google Sheet (English US locale) on .
Common errors
- Both start_date and end_date are counted when they are working days. Two equal weekdays give 1, not 0.
- If start_date is after end_date the result is negative, not an error.
- Weekends are fixed as Saturday and Sunday. For other weekends use NETWORKDAYS.INTL.
- Holidays are not known to Sheets. Without the third argument, public holidays count as working days.
Compared with Excel
Same syntax in Excel.