NETWORKDAYS in Google Sheets: syntax and examples

NETWORKDAYS counts the days from Monday to Friday between two dates, both ends included. A list of holidays removes more days, so it fits delivery times and invoice terms.

Syntax

NETWORKDAYS(start_date, end_date, [holidays])

Arguments

ArgumentTypeRequiredWhat it does
start_datedateyesFirst day of the period, counted if it is a working day.
end_datedateyesLast day of the period, also counted.
holidaysrangenoDates to skip, in addition to Saturdays and Sundays.

Examples

The examples use this table, starting in A1:

Holidays
46356
46386
=NETWORKDAYS(DATE(2026,11,2), DATE(2026,11,30))

Result: 21

Working days in November 2026 from the 2nd to the 30th, weekends excluded.

Run in a Google Sheet (English US locale) on .

=NETWORKDAYS(DATE(2026,11,2), DATE(2026,11,30), A2)

Result: 20

The same period minus one holiday (30 November, in A2).

Run in a Google Sheet (English US locale) on .

=NETWORKDAYS(DATE(2026,12,1), DATE(2026,12,31), A2:A3)

Result: 22

December with two holidays in the list (30 Nov is outside, 30 Dec is inside).

Run in a Google Sheet (English US locale) on .

=NETWORKDAYS(DATE(2026,11,9), DATE(2026,11,9))

Result: 1

Start and end on the same working day count as 1.

Run in a Google Sheet (English US locale) on .

=NETWORKDAYS(DATE(2026,11,30), DATE(2026,11,2))

Result: -21

Start after end: the result is negative.

Run in a Google Sheet (English US locale) on .

Common errors

  • Both start_date and end_date are counted when they are working days. Two equal weekdays give 1, not 0.
  • If start_date is after end_date the result is negative, not an error.
  • Weekends are fixed as Saturday and Sunday. For other weekends use NETWORKDAYS.INTL.
  • Holidays are not known to Sheets. Without the third argument, public holidays count as working days.

Compared with Excel