JQL function
endOfMonth() in JQL: syntax and examples
endOfMonth() stands for the end of the current month. Use it for month-close reviews and "due this month" filters. Offsets move it by months, or by days when you write a unit.
Syntax
endOfMonth()
endOfMonth("inc")
Arguments
| Argument | What it does | Optional |
|---|---|---|
inc | Optional offset in the form (+/-)nn(y|M|w|d|h|m). With no unit it counts months, so "+1" is the same as "+1M". With no sign, plus is assumed. | yes |
Works with
- Fields: Created, Due, Resolved, Updated, custom Date or Date/Time fields
- Operators: =, !=, >, >=, <, <=, and inside WAS, WAS IN, WAS NOT, WAS NOT IN, CHANGED predicates
- Not with: ~, !~, IS, IS NOT, IN, NOT IN
Examples
duedate >= startOfMonth() AND duedate <= endOfMonth() ORDER BY duedate ASCEvery deadline in the current month, in date order. The base for a month-close review.
Run on Jira Cloud on .
duedate >= startOfDay() AND duedate <= endOfMonth() AND statusCategory != Done ORDER BY duedate ASCOpen work that still has to land before the month ends.
Run on Jira Cloud on .
duedate <= endOfMonth("+1") AND duedate > endOfMonth() ORDER BY duedate ASCNext month's deadlines only. Useful in a planning meeting at month end.
Run on Jira Cloud on .
duedate <= endOfMonth("+15d") AND statusCategory != DoneOpen work due by mid-month after this one. The unit "d" is added to the month end, so it reaches 15 days into next month.
Run on Jira Cloud on .
duedate = endOfMonth()Work due on the last day of the month, for a final-day checklist.
Run on Jira Cloud on .
Pitfalls
endOfMonth("+1")is the end of next month, not 30 days from now. The offset unit decides: "+1" and "+1M" are a month, "+1d" is a day.- The doc example
due < endOfMonth()drops work due on the last date, because a due date has no time. Use<=for "by the end of the month" (checked on Jira Cloud, November 2026). - Short months are handled for you. You do not need to write 28, 30 or 31, which is the whole reason to use the function instead of a typed date in a saved filter.
Questions and answers
Which JQL gives work items due this month?
Use duedate >= startOfMonth() AND duedate <= endOfMonth(). Add statusCategory != Done to keep only open work.