# WORKDAY in Google Sheets: syntax and examples

URL: https://goingstellar.ro/reference/sheets/workday/

WORKDAY adds working days to a date and returns the resulting date. Saturdays, Sundays and any listed holidays are skipped, which makes it a good fit for deadlines and delivery dates.

## Syntax

```
WORKDAY(start_date, num_days, [holidays])
```

## Arguments

- `start_date` (date, required: yes): The date to count from. It is not counted itself.
- `num_days` (number, required: yes): Working days to add. Negative goes back in time.
- `holidays` (range, required: no): Dates to skip, in addition to Saturdays and Sundays.

## Examples

The examples use this table, starting in A1:

| Holidays |
|---|
| 46356 |

```
=WORKDAY(DATE(2026,11,23), 5)
```

Result: `11/30/2026`

Five working days after Monday 23 November: the following Monday. Run in a Google Sheet (English US locale) on 2026-11-29.

```
=WORKDAY(DATE(2026,11,27), 1)
```

Result: `11/30/2026`

One working day after a Friday is the Monday after. Run in a Google Sheet (English US locale) on 2026-11-29.

```
=WORKDAY(DATE(2026,11,27), 1, A2)
```

Result: `12/1/2026`

The Monday 30 November is a holiday in A2, so the result moves to Tuesday. Run in a Google Sheet (English US locale) on 2026-11-29.

```
=WORKDAY(DATE(2026,11,30), -3)
```

Result: `11/25/2026`

A negative num_days counts backwards. Run in a Google Sheet (English US locale) on 2026-11-29.

```
=WORKDAY(DATE(2026,11,29), 0)
```

Result: `11/29/2026`

Zero days from a Sunday returns the same Sunday. Run in a Google Sheet (English US locale) on 2026-11-29.

## Common errors

- start_date is not counted. One working day after Friday is Monday, three calendar days later.
- The result is a date serial number. A bare WORKDAY cell shows it as a date in the locale format (11/30/2026 or 30.11.2026), but inside arithmetic it is a number. Use TEXT for a fixed format.
- Public holidays are not known to Sheets. List them in the third argument, or deadlines land on days off.
- Weekends are fixed as Saturday and Sunday. For a different weekend use WORKDAY.INTL.

## Compared with Excel

Same syntax in Excel.

## Related functions

- [NETWORKDAYS](https://goingstellar.ro/reference/sheets/networkdays/)
- [EDATE](https://goingstellar.ro/reference/sheets/edate/)
- [EOMONTH](https://goingstellar.ro/reference/sheets/eomonth/)
- [DATE](https://goingstellar.ro/reference/sheets/date/)

## Sources

- [WORKDAY (Docs Editors Help)](https://support.google.com/docs/answer/3093059)