# CHANGED operator in JQL: syntax and examples

URL: https://goingstellar.ro/reference/jql/changed-operator/

CHANGED matches work items where a field has been changed at least once. Add FROM and TO to name the old and new value, and BY, AFTER, BEFORE, DURING or ON to say who changed it and when. It is the operator for audit-style questions.

## Syntax

```
field CHANGED
field CHANGED [FROM "old"] [TO "new"] [BY user] [AFTER "date"] [BEFORE "date"] [ON "date"] [DURING ("date1","date2")]
```

## Arguments

- `FROM` (optional: no): The old value.
- `TO` (optional: no): The new value.
- `BY` (optional: no): The user who made the change.
- `AFTER / BEFORE / ON` (optional: no): A date boundary. Functions such as startOfWeek() are accepted.
- `DURING` (optional: no): A pair of dates in parentheses.

## Works with

- Fields: Assignee, Fix Version, Priority, Reporter, Resolution, Status
- Operators: CHANGED itself, with the predicates above
- Not with: other fields. Summary, Labels and Due date are rejected with "History searches do not support the  'labels' field." and the same text for the other names

## Examples

```
assignee CHANGED
```

Work that was reassigned at least once. A quick way to spot handovers. Run on Jira Cloud on 2026-11-29.

```
status CHANGED FROM "In Progress" TO "Done"
```

Work that went straight from In Progress to Done, with no review step between. Run on Jira Cloud on 2026-11-29.

```
status CHANGED FROM "To Do" TO "In Progress" DURING (startOfWeek(), now())
```

Work that was started this week, for a weekly progress note. Run on Jira Cloud on 2026-11-29.

```
priority CHANGED FROM "Medium" TO "High" AND project = WEB ORDER BY updated DESC
```

Website items that were escalated from Medium to High, newest activity first. Run on Jira Cloud on 2026-11-29.

```
assignee CHANGED BY currentUser() AFTER startOfDay("-7d")
```

Reassignments you made in the last seven days. Run on Jira Cloud on 2026-11-29.

## Pitfalls

- `labels CHANGED` fails with "History searches do not support the  'labels' field." The same happens for `summary` and `duedate`. Only six fields have searchable history.
- AFTER and BEFORE accept functions, so `status CHANGED BEFORE endOfWeek() AFTER startOfWeek()` limits the search to the current week (checked on Jira Cloud, November 2026).
- Plain `status CHANGED` matches any item that ever moved. Add a date predicate when you want a recent window.

## Ready-made queries

- [Moved to Done in the last N days](https://goingstellar.ro/tools/jql-examples/#done-last-n-days)

## Questions and answers

### How do I find issues that changed status this week?

Use status CHANGED AFTER startOfWeek(). Add TO "Done" to find only the ones that were completed.

## Related

- [WAS](https://goingstellar.ro/reference/jql/was-operator/)
- [WAS IN](https://goingstellar.ro/reference/jql/was-in-operator/)
- [status](https://goingstellar.ro/reference/jql/status-field/)
- [assignee](https://goingstellar.ro/reference/jql/assignee-field/)
- [priority](https://goingstellar.ro/reference/jql/priority-field/)
- [startOfWeek()](https://goingstellar.ro/reference/jql/startofweek/)

## Sources

- [JQL operators (Atlassian Support, Jira Cloud)](https://support.atlassian.com/jira-software-cloud/docs/jql-operators/)