# Jira velocity chart: commitment, completed work and how velocity is calculated

*The velocity chart compares what a scrum team committed to with what it completed, sprint by sprint. Here is what each bar means, how Jira calculates velocity, and what the chart leaves out.*

> Jira · Scrum · Reports · 2026-11-29 · https://goingstellar.ro/methods/jira-velocity-chart/

## Key points

- The velocity chart shows commitment and completed work per sprint for scrum spaces.
- Commitment is fixed at sprint start; completed includes later scope changes.
- Velocity is the average of completed estimates over recent sprints.
- Subtask estimates are not counted; only parent work items are.
- Compare a team with its own history, not with other teams.

## What it is for

Atlassian describes the velocity chart as showing the average amount of work a scrum team completes during a sprint. Teams use it to predict how quickly they can work through the backlog, because it tracks forecast and completed work over several sprints; the more sprints, the more accurate the forecast. It is available only in spaces that use the Scrum template.

## Open it

In a company-managed software space, open **Reports** from the sidebar and choose **Velocity Chart**. It shows the most recent sprints the team completed.

## Reading the bars

**Commitment**, the grey bar, is the total estimate of all work items in the sprint when it started. Work added later, or estimates changed after the start, are not included in it.

**Completed**, the green bar, is the total of completed estimates when the sprint ended, and it does include scope changes made after the start.

The black line is the average completed work across the sprints shown. The vertical axis is the board's estimation statistic: story points, original time, work item count or any numeric custom field.

## How velocity is calculated

Velocity is the average of the completed estimates over the last several sprints. Atlassian's own example averages six sprints: (17.5 + 13.5 + 38.5 + 18 + 33 + 28) / 6 = 24.75. Estimates on subtasks are not included; only parent work items count. Like the burndown, the chart only includes work items in the board's saved filter, and treats as Done only statuses mapped to the right-most column.

## Using it well

Velocity compares a team with its own past, not with another team: two teams' story points are not the same unit. A large gap between commitment and completed, sprint after sprint, says more about planning than about speed. And the number only becomes useful once the team estimates consistently, which is a conversation, not a report.

## Sources

1. [Atlassian Support: View and understand the velocity chart](https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/)

## Questions and answers

### How is velocity calculated in Jira?

Jira averages the total completed estimates over the last several sprints shown on the chart.

### What is the difference between commitment and completed in Jira?

Commitment is the total estimate when the sprint started; completed is the total of finished estimates when it ended, including scope added during the sprint.

### Why is the velocity chart not available in my Jira space?

It is only available in spaces that use the Scrum template.

## How to cite

**Cite this as:** Going Stellar (2026). *Jira velocity chart: commitment, completed work and how velocity is calculated*. GOING STELLAR S.R.L.. https://goingstellar.ro/methods/jira-velocity-chart/

```bibtex
@misc{goingstellar2026jira,
  title  = {Jira velocity chart: commitment, completed work and how velocity is calculated},
  author = {{Going Stellar}},
  year   = {2026},
  url    = {https://goingstellar.ro/methods/jira-velocity-chart/},
  note   = {2026-11-29}
}
```

Licence. Free to quote with attribution.

## Also available

- This page as HTML: https://goingstellar.ro/methods/jira-velocity-chart/
- Same article in Romanian: https://goingstellar.ro/ro/metode/graficul-de-viteza-in-jira/