# Getting started with Deadliner for Jira

*Install Deadliner, turn on due date reminders for a Jira project, see which issues get a comment and when, and switch on the daily digest e-mail for the project lead.*

> Jira · Deadliner · Setup · 2026-11-29 · https://goingstellar.ro/methods/getting-started-with-deadliner/

## Key points

- Turn Deadliner on per project, from the Deadliner page in the project sidebar.
- Reminders are comments that @mention the assignee: one before the due date, one when overdue.
- Only open issues with a due date and an assignee are checked; overdue ones within 14 days.
- The daily digest e-mails the project lead and works on its own, even with reminders off.
- A licence lets you choose the lead time (1 to 30 days); without one it is 2 days.

## 1. Install it

Installing needs an organization admin or a site admin. Atlassian's steps: open the app's page on marketplace.atlassian.com, select **Get it now** or **Try it free**, pick the site, select **Review**, then confirm. A message tells you the app was added. If your network filters domains, Atlassian asks you to allow `*.cdn.prod.atlassian-dev.net`, which is where Forge apps load their screens from.

Deadliner adds one page to Jira: **Deadliner** in each project's sidebar. Settings are per project, so nothing happens until you turn it on in a project.

## 2. Turn on reminders for a project

Open the project and select **Deadliner** in the sidebar. Under **Reminders for this project**, select **Turn on**. The status changes to ON, and from then on the daily scheduled run checks the project. To see it work straight away, select **Send reminders now**.

Saving settings or sending reminders needs permission to add comments in that project. Reminders sent with **Send reminders now** are posted under your name; the daily run posts them as the app.

## 3. What a reminder looks like

A reminder is a comment on the issue that @mentions the assignee, so it reaches them where they already work. Before the due date it reads "⏰ reminder: this issue is due YYYY-MM-DD". When the issue is overdue it reads "⏰ this issue is overdue (was due YYYY-MM-DD)".

Each issue gets at most one "due" comment and one "overdue" comment per due date, so the same deadline is not repeated every day. Move the due date and the new date gets its own reminders.

## 4. Which issues it checks

Open issues with a due date and an assignee. Issues in a Done status, without a due date, or without an assignee are skipped. Overdue issues are picked up if they became overdue in the last 14 days; an issue that has been overdue longer than that gets no new comment. Dates are worked out in UTC.

## 5. Turn on the daily digest

Under **Daily digest e-mail**, select **Turn on**. Once a day the project lead gets one e-mail, sent through Jira's own notification, listing what is overdue and what is due soon. No e-mail goes out on a day with nothing to report, and a project without a lead gets none.

The digest is separate from reminders: it can be on while reminders are off. **Send digest now** sends one immediately. The page itself also shows the **Overdue** and **Due soon** tables at any time.

## 6. Without a licence and with one

Reminders, overdue alerts, the digest and both tables all work without a licence. The one difference is the lead time: without a licence reminders go out 2 days before the due date; with one you choose 1 to 30 days in **Remind (days before due)** and select **Save**. During an Atlassian trial, a line on the page says until which date the custom lead time is included.

## 7. Limits worth knowing

Each run checks up to 2,000 issues. If a run reaches a limit it stops cleanly and the next run carries on, and the tables say when they are cut short. Deadliner reads and writes only inside Jira and keeps its settings in Forge app storage.

## Sources

1. [Atlassian Support: Install and manage app access](https://support.atlassian.com/organization-administration/docs/installing-and-managing-app-access/)
2. [Atlassian Marketplace: Deadliner (listing, version 3.6.0)](https://marketplace.atlassian.com/apps/3520227196/deadliner-due-date-reminders-overdue-alerts)

## Questions and answers

### Why did an issue get no reminder?

It may have no assignee, no due date, a Done status, or it became overdue more than 14 days ago. Check also that reminders are ON for that project.

### Will it comment every day?

No. Each due date gets at most one reminder before it and one when it is overdue. A new due date starts again.

### Who gets the digest?

The project lead, once a day, only when something is overdue or due soon. It is opt-in per project.

## How to cite

**Cite this as:** Going Stellar (2026). *Getting started with Deadliner for Jira*. GOING STELLAR S.R.L.. https://goingstellar.ro/methods/getting-started-with-deadliner/

```bibtex
@misc{goingstellar2026getting,
  title  = {Getting started with Deadliner for Jira},
  author = {{Going Stellar}},
  year   = {2026},
  url    = {https://goingstellar.ro/methods/getting-started-with-deadliner/},
  note   = {2026-11-29}
}
```

Licence. Free to quote with attribution.